FFT Activities

in the Kootenay TSA
 

For further information contact the FFT Recipient

True Blue Ventures
Contact: Joanne Leesing - joanne.leesing@forestsfortomorrow.ca

DKL update April 21, 2008

Impeded Stands
The file review portion of the impeded stands project is now complete!  Over 500 files, representing approximately 16,000 ha were reviewed in early 2008.  As expected, the file review did not yield many FG openings, generally due to the vintage of the data on file.  Many areas are now scheduled for field review in 2008 and it is hoped that this will help to address the ‘impeded’ issues.

Hamill Creek (click for aerial photo)
The two plantations that were partially destroyed in the fire of 2007 will be spring planted in 2008.  It is hoped that this planting will take place in the early weeks of May.  Perimeter DTA will take place just before planting.

Schroeder Creek (click for aerial photo)
Licensee salvage plans have been finalized and a preliminary survey plan has been made for this area.  Wildfire assessments will be completed sometime during the summer of 2008.

Sitkum Creek (click for aerial photo)
Licensee salvage plans have not been communicated to RAH at this point.  Once these plans have been made, wildfire assessment surveys can take place.  Planting in summer 2009 is anticipated.

Kuskanook (click for aerial photo)
Spring planting in Skelly Creek and summer planting in Sanca Creek will complete the planting for this fire area.  This planting contract has been awarded to the Ktunaxa Kinbasket Development Corp, a FN contractor from the East Kootenays.

An overall FFT operational map was created for this area over the winter and is now available.

Mission (click for aerial photo)
Other than reconnaissance surveys, no activities are planned for this area.  Spring 2009 will see the completion of planting in this area.

Skinner-Madden (click for aerial photo)
DTA and planting contracts have been awarded for summer work in 2008. The Ktunaxa Kinbasket Development Corp. has been awarded one of the three planting contracts.  The DTA work is expected to commence in early June, with planting planned for late June-early July.  Heli pads will be constructed throughout the fire area.

Lake Creek (click for aerial photo)
DTA and planting contracts have been awarded for summer work in 2008.  The Ktunaxa Kinbasket Development Corp. has been awarded the DTA work for this area.

All work is expected to begin in early July.