Minutes of FFT Seed Group Meeting. Please report any errors
or omissions to whole group.
1) Seed use and reporting requirements in FFT/FIA planting
contracts.
- FIA/FTT planting and reporting standards should set
a higher same as CF standards - monitor results before
recommend anything different.
- Consider FFT MoFR policy for higher standards (highest
GW)
- Proposed changes to FIA/FFT standards (see attached
for proposed changes and comments).
FIA FFT Seed
Standards.doc
- Action: FFT seed group members to provide
comment on attached proposed changes (by April 10 please)
- Brian to forward proposed changes to FIA/FFT standards
to Rick Brand (FIA), Colene Wood (MoE - eco restoration),
Al McDonald (BCTS), Ian Brown (PWC), and CF Standards
Steering Committee.
- Upon agreement - forward recommended changes to Brian
R/Nigel to incorporate.
- Need to develop standards for assessing impeded stands
(stands that did not meet free-growing and for which treatments
need to be prescribed). Requires seed transfer assessment
component (maybe seed was off-site).
- Action:Leslie, Brian and Mike to discuss
standards for impeded stands.
2) Review of last year's work
a) Yoursry - on Pli Seed Utilization project (1st year).
- Stratification treatments breaks difference in clonal
dormancy, germination rates etc.
- Recommend single sowing to increase seedling yields
- Further work to verify results with seed from orchard
307, and bulked lots and in nursery.
- Small percent improvement can increase # seedlings,
ha, AAC in a large program such as Pli
- Need to consider how, when to move results and recommendations
(after this year's results) into policy and operations.
- Research methods - but not results - could be applied
to other spp.
- Action: Comments on report to Yousry
b) Leslie - Seed Analyses - Genesis and Timberline Contracts.
- Mark Faliszewski report - received year end
- Action: group members to review and
provide written comments to all (by April 13 please)
- Timberline report forthcoming - plan face-to-face
meeting to discuss after delivery (May)
- FGC plans for Jack Woods's report? Difficult to read/interpret
his tables.
- Client expectations high for assessing MPB seed implications,
facilitating collections but high level of uncertainty
harvest and reforestation.
- TIB staff to meet this Wednesday to discuss CF challenge/question
and short- and long-term strategies for addressing.
c) Heather - FFT sowing requests, services,sales and
processing $
- Lots of Pli collection activity occurring - dynamic,
difficult to know what's happening where (e.g. lots
being processed by Silva Seed).
- No indication collections being guided by an overarching
plan - everyone collecting what they can.
- $75,000 spent last year on seed sales, services and
cone and seed processing.
3) 2006/07 FFT work plan seed projects and $
- Budgets not finalized. $ very tight this year.
- Regions instructed not to do surveys, etc. to be 3rd
party delivery - so hard to plan.
- $60k for Pli project Ok.
- FFT TIB - perhaps $75k for strategic planning and information
gathering, couple work with other funding sources FIA,
GRIM etc.
- TIB to discuss CF request for MPB seed analysis and
longer-term project on Wednesday - refine projects, keep
regions in the loop. Also need to coordinate with FGC
to ensure no overlap of work (e.g. FIA incremental $)
- $100,000 anticipated for seed sales, services and cone
and seed processing - in FPB's FFT budget
4) Other
- Canfor did FFT Pli collection in Mackenzie via PWC in
coop with NIFR. Processing to be paid by Anna. Seed to
be owned by MoF 28 (NIFR FFT)
Brian Barber, RPF
Technical Advisor
Tree Improvement Branch
BC Forest Service
ph (250) 356-0888
|
|